Grain Belt, SunZia and the Return of Long-Distance HVDC in the US

Written By: admin
Published On: November 19, 2026

Article

Grain Belt, SunZia and the Return of Long-Distance HVDC in the US

Written By: admin
Published On: November 19, 2026

For two decades, US long-distance HVDC was a story of proposals that never got built. In 2026, power is flowing on a new one, and others are moving toward construction.

The United States pioneered long-distance HVDC with the Pacific DC Intertie in the 1970s, then built very little for decades. Merchant lines such as Grain Belt Express and SunZia spent more than ten years in permitting.

That is changing, and with it the outlook for converter, cable and transformer suppliers. Globally, PTR expects annual HVDC capacity additions to nearly triple between 2025 and 2030.

SunZia: proof that it can be done

In June 2026, Pattern Energy’s SunZia project was inaugurated, carrying wind power from New Mexico to customers in Arizona and California over a roughly 550-mile line.

Its HVDC converters, supplied by Hitachi Energy, make it a 3 GW-class voltage source converter link on an overhead corridor, a configuration that a few years ago would almost certainly have used older line-commutated technology.

Grain Belt Express: pressing on

Invenergy’s Grain Belt Express is planned to carry up to 5 GW from Kansas toward Missouri, Illinois and Indiana. The developer selected Siemens Energy for HVDC technology and in 2025 awarded about $1.7 billion of construction contracts to Quanta Services and Kiewit.

In July 2025 the Department of Energy cancelled a $4.9 billion conditional loan guarantee for the project; Invenergy said it would proceed without it. The episode shows both the momentum and the policy risk around these projects.

Why HVDC, and why VSC

  • Distance: beyond the break-even distance, HVDC carries more power per corridor with lower losses than AC.
  • Controllability: HVDC lets operators set power flows between regions, which is valuable as data-center load concentrates in a few hubs.
  • VSC capability: voltage source converters now reach the 3,000 MW class and add voltage support and fault response. Developers such as TransWest Express and Southern Spirit have moved from LCC concepts to VSC.

What still holds projects back

  • Permits and routes: multi-state lines need approvals along the full route, and local objections can force redesigns.
  • Funding and policy: federal support can change quickly, as Grain Belt shows.
  • Equipment: converter stations and large transformers carry multi-year lead times, so delivery slots are booked years in advance.

What this means

  • For suppliers: the US is becoming a real HVDC market again, with VSC as the default for new corridors.
  • For developers and utilities: securing converter capacity early is as important as securing permits.

About the data. Figures in this article come from PTR’s Global HVDC Market Report 2025-2030, which sizes annual HVDC capacity additions to 2030 by region and technology and includes a database of 271 identified projects. Request a sample at sales@ptr.inc.